Harris County 2015 Non-Housing & Flood Monthly Report

Project Organization Project Name Total Project Cost Total CDBG-DR Award Date Court Approved Date Awarded by GLO
Precinct 1 Flood and Drainage Improvements $300,422.00 $186,422.00 6/12/2018 5/1/2018
Precinct 2 Western Homes Street Improvements $516,977.65 $461,864.00 6/12/2018 5/1/2018
Precinct 3 Bear Creek Pioneers Park Sewer Facilities $134,500.01 $102,836.00 6/12/2018 5/1/2018
Harris County Flood Control District Helm Rd. Drainage Improvements $975,853.00 $975,853.00 6/12/2018 5/1/2018
 

Total

$1,927,752.66

$1,726,975.00

 

2015 Flood Monthly Report

Non-Housing Flood Projects Update Report (Infrastructure and Planning Studies)

For more information on Non-Housing program, please contact the HCCSD Disaster Recovery staff at (832) 927-4700 for assistance.

2015 Floods Round 1 Monthly Project Status Report - 2020